OK, they're not on yet, but this huge stack of trusses that was craned in after lunch certainly rates a mention as today's latest exciting instalment.
Despite long delays in the drafting, estimating and contracts phases of this project, the construction team is barely stopping for smoko!
Work began with a site cut on September 16, but didn't fully get under way until September 29, when the survey pegs went in. If we count from then, we are now up to Day 16 of the active build.
Total construction time is estimated at 130 days, plus 85 days for delays (weekends, Christmas and rain), with completion in April.
The current plan is for lockup before the Christmas shutdown. Hmmm, sensible!